Dongfeng completes 47,000 m² gigacasting plant 25 days early

Article Sponsored by:

CMiC Global

CMIC Global Logo

Since 1974, CMiC has been a global leader in enterprise software for the construction industry. Headquartered in Toronto, Canada, CMiC delivers a fully integrated platform that streamlines project management, financials, and field operations.

With a focus on innovation and customer success, CMiC empowers construction firms to enhance efficiency, improve collaboration, and make data-driven decisions. Trusted by industry leaders worldwide, CMiC continues to shape the future of construction technology.

Read More About CMiC: 

Interior of a gigacasting plant showing massive 16,000‑tonne and 10,000‑tonne die casting lines with cranes and workers

China, September 8, 2025

News Summary

Dongfeng has finished construction of a 47,000 m² gigacasting factory 25 days ahead of schedule, allowing earlier equipment installation and commissioning. The single‑phase building will house ultra‑large die‑casting lines including a 16,000‑tonne unit and a 10,000‑tonne unit, positioning the company at the forefront of large‑format casting. Using Building Information Modeling (BIM) sped coordination and delivery. The project targets phased production capacity with an initial annual output goal of 200,000 components and a later scale‑up to 600,000 after additional lines are added. Investment is about 1 billion yuan and lines will be brought online gradually.

Dongfeng completes 47,000 m² gigacasting plant 25 days early; mass production set for June 2026

What happened: A large die‑casting plant built for an automaker was finished 25 days ahead of schedule. The facility covers about 47,000 square meters and will form the main production base for the automaker’s gigacasting program. Construction started in November 2024 and the factory building was completed in one phase, with casting lines to be installed and brought online in stages. Full mass production is expected to begin in June 2026.

Why this matters

The plant will host two very large integrated die‑casting lines in its first phase: one using a 16,000‑tonne machine and one using a 10,000‑tonne machine. These are among the largest die‑casting machines in use and are intended to produce big, single‑piece structural parts such as rear floor assemblies and battery casings for new energy vehicles (NEVs). Once running, the lines are expected to lift production speed and reduce the number of separate body parts and welds needed, which can lower cost and save factory space.

How the project was built so fast

The construction team applied Building Information Modeling (BIM) to streamline design coordination and on‑site work. The use of BIM helped identify clashes, coordinate trades and speed up the handover process, allowing the building to be turned over nearly a month before contract deadlines. The physical plant is complete; the casting equipment will be installed over time under a two‑phase plan.

Phases, cost and capacity

The total investment for the project is around 1 billion yuan. In the first phase, the plant will add one 10,000‑tonne line and one 16,000‑tonne line. That initial setup gives the site an annual capacity of about 200,000 components. A second phase will add four more lines, taking total annual output to roughly 600,000 components once complete.

What gigacasting is and why firms use it

Gigacasting uses very large die‑casting machines to make multiple vehicle parts as a single structural component. Molten metal is forced into a die under high pressure, cooled, ejected and trimmed to make a big part in one step. The approach can cut the number of parts and welds, shorten assembly lines, reduce labor and save space. It can also improve structural strength and crash performance when parts are designed correctly. Typical target parts include large underbody sections and battery trays.

Industry context

Several automakers and suppliers have moved to one‑piece die‑cast parts for EVs, citing weight reduction, lower part counts and cost savings. Some factories already use large die‑casting presses to form rear or front underbody sections. The move to ever‑larger machines aims to combine more sections into single pieces and speed up production cycles. Suppliers of prototype molds and sand test molds have been used to speed design checks and reduce validation costs during the switch to large‑scale die casting.

Tradeoffs and challenges

Big cast parts can change repair processes and collision economics: damaged cars may be harder or more expensive to repair at the part level. Large machines have high up‑front costs and require special alloys, tooling and process control to avoid distortion and casting defects. Design, testing and heat treatment processes are being adjusted by casting specialists to handle these challenges.

Next steps for the plant

With the factory shell complete, equipment installation and commissioning will follow. The first two lines are slated to be installed in the initial phase, feeding the planned 200,000‑unit yearly output capacity. Additional lines will be added later to reach the full 600,000 annual capacity. Mass production of gigacast components is planned to start in June 2026.

Photo and announcement note

The construction group that announced completion included a photo with the notice. The announcement credited the construction team’s digital planning tools as key to finishing early.


FAQ

Q: What is the size of the new plant?

A: The completed factory building covers approximately 47,000 square meters.

Q: When did construction start and when is mass production expected?

A: Construction began in November 2024. Mass production is expected to start in June 2026.

Q: What casting machines will the plant use?

A: In the first phase the plant will install a 16,000‑tonne and a 10,000‑tonne gigacasting line. More lines are planned in a later phase.

Q: How many parts can the plant make each year?

A: Phase one gives an annual capacity of about 200,000 components. After phase two adds four more lines, capacity should reach about 600,000 components per year.

Q: Why use gigacasting for EV parts?

A: Gigacasting can reduce part count and welds, cut assembly time and cost, save factory space, lower weight and improve structural performance when parts are properly designed and validated.

Q: What are the downsides?

A: Drawbacks include high initial investment, tougher repairability for large single pieces, and technical challenges in alloy and process control to avoid defects or distortion.

Key features at a glance

Feature Details
Factory size 47,000 m²
Construction timeline Started November 2024; building finished 25 days early
Key tech used in construction Building Information Modeling (BIM)
Installed lines (phase 1) One 16,000‑tonne and one 10,000‑tonne gigacasting line
Phase 1 capacity 200,000 components per year
Full capacity (both phases) 600,000 components per year
Planned start of mass production June 2026
Estimated investment Around 1 billion yuan

Deeper Dive: News & Info About This Topic

Additional Resources

Construction NY News
Author: Construction NY News

NEW YORK STAFF WRITER The NEW YORK STAFF WRITER represents the experienced team at constructionnynews.com, your go-to source for actionable local news and information in New York and beyond. Specializing in "news you can use," we cover essential topics like product reviews for personal and business needs, local business directories, politics, real estate trends, neighborhood insights, and state news affecting the area—with deep expertise drawn from years of dedicated reporting and strong community input, including local press releases and business updates. We deliver top reporting on high-value events such as the New York Build Expo, infrastructure breakthroughs, and cutting-edge construction technology showcases. Our coverage extends to key organizations like the Associated General Contractors of New York State and the Building Trades Employers' Association, plus leading businesses in construction and real estate that power the local economy such as Turner Construction Company and CMiC Global. As part of the broader network, including constructioncanews.com, constructiontxnews.com, and constructionflnews.com, we provide comprehensive, credible insights into the dynamic construction landscape across multiple states.

Stay Connected

More Updates

Would You Like To Add Your Business?

WordPress Ads